We respond to short delivery times! We provide integrated production from design to manufacturing and testing, including welding and machining, all in our own factory.
We would like to introduce a case where we manufactured a "rotary valve" for a semiconductor manufacturer that is currently constructing a new factory.
The company required a specially designed rotary valve and needed to obtain it within three months due to project timelines.
Our company was able to achieve a significantly compressed delivery schedule because we handle everything in-house, from design and manufacturing to verification, welding, and machining. We were able to deliver by the desired date.
[Challenges]
■ A specially designed rotary valve was needed.
■ They consulted with a manufacturer they had previously worked with, but were told it would take six months for delivery.
■ Due to the timeline for the new factory, they needed to obtain it within three months.
■ Consulting with other manufacturers would mean starting from scratch, which would not meet the deadline.
*For more details, please refer to the PDF document or feel free to contact us.