[Case Study] Production Scheduler Panasonic Corporation
The planning time has been shortened from "4 people for 2 days to 2 people for 1 day," and the production lead time has been reduced from "2 weeks to 1 week!"
At the Hyogo factory, planning was done by hand on paper, and an old scheduler was used for some processes, but it was not very effective. Therefore, we introduced 'Asprova'. This allowed us to create time-based process plans that could not be handled by hand before. Additionally, by being able to issue work instructions on an hourly basis, we were able to reduce the production lead time from 2 weeks to 1 week. [Challenges] - Planning was done by hand on paper, requiring two dedicated personnel on-site to manage rotations. - The old scheduler was used, but it was not very effective. - During the planning reviews conducted twice a week, the process plan had to be rewritten from scratch each time a modification was made, which was a significant burden. *For more details, please refer to the PDF document or feel free to contact us.